Entering Data for a Previous Date

There are scenario's when the user may want to add achievements for a previous date.

  1. Navigate Assessments I Individual I Assessments
  2. Make your selection in the Selection panel then Display 
  3. Just under the Achievement drop down box is a date option 
  4.   Change the date by either using the calendar option or by manually editing the date.
  5. Any achievement added will now show as being added on the edited date